Multi-product Pipeline (MPP) and Trans-Sabah Gas Pipeline (TSGP) Contracts
Disclosure Timeline
-
05 Jul, 2018
-
Ministry of Finance Media Release on SSER and ECRL
(Lim Guan Eng, Minister of Finance)
Services & Operation Suspension Notice Issued for Suria Synergy Energy Resources (SSER) with a Construction Cost of RM9.4 Billion & East Coast Rail Link (ECRL) cost of RM81 Billion
Directly implicated: Suria Strategic Energy Resources Sdn Bhd , China Petroleum Pipeline Bureau
-
11 Jun, 2018
-
MACC raids SSER offices, Lim blasts Najib for evading the real issues
(FARIK ZOLKEPLI, The Star)
The Malaysian Anti-Corruption Commission (MACC) has raided the office of Suria Strategic Energy Resources Sdn Bhd (SSER), the company which awarded two pipeline projects worth RM9.4bil
Directly implicated: Suria Strategic Energy Resources Sdn Bhd , China Petroleum Pipeline Bureau
Notes
MPP and TSGP projects, with a total construction cost of RM9.4 billion, were awarded to China Petroleum Pipeline Bureau (CPPB). SSER was paid RM8.3 billion or 88% of the project’s construction value of RM9.4 billion, even though progressive work completion (that has not been audited) is only at 13%. These SSER contracts worth RM9.4 billion have not taken into account cost related to land acquisition, two expert consultancy agreements, and a maintanence agreement; comprising a total additional cost of RM1.7 billion.
Subitems
- Ministry of Finance Media Release on SSER and ECRL (Issue Source)